11-22-16 Construction Update
11-22-16 Construction UpdateProgress on the construction of the new Groveport Madison High School is moving very quickly. The exterior concrete block walls of the gymnasiums and athletics wing are done, as are the load-bearing walls of the dining commons, kitchen and auditorium. Work is also progressing on the load-bearing walls of the academic wings. To date, masons have laid 134,885 concrete blocks, representing approximately 51 percent of the total concrete blocks to be laid for the entire structure.

The project remains on schedule and within budget. Be sure to check out our photos and aerial videos of the construction work.